5th June 2014

Discovery Point - Watervue 'Topping Out' Celebration

The project team at Discovery Point - Watervue,  NSW celebrated the “Topping Out” milestone on Friday 30 May 2014 after reaching completion of the building’s structure.

Hindmarsh celebrated the milestone with a site BBQ lunch which site personnel and subcontractors attended.

The Watervue structure was based on a 6 to 7 day cycle with a routine for services and key contributing contractors, turn around for floor by floor completion from Ground floor to Plant level. Level 1 formwork deck commenced in mid January. Work on the 6 day cycle Plant level was poured in late May.

The project is on track for completion later this year.

Congratulations to the project team led by Senior Project Manager Rob Vranjesevic.